Dewatering an Ontario Commercial Site: Permit to Take Water or EASR Registration, and Who Owes What While the Pumps Run
Ontario’s water-taking rules for construction sites are easier to follow when you sort them by person: the owner who picks the route, the two professionals who sign the reports, the crew that runs the pumps, and the City and Province that each want to see something different.
Whose name has to be on the paperwork when an Ontario construction site pumps out groundwater, and which paperwork is it?
The rules attach to the person taking the water, and the default under Ontario law is a Permit to Take Water once more than 50,000 litres are taken on any day. For dewatering a construction site, that default is replaced by a registration on the Environmental Activity and Sector Registry (EASR), but only after two qualified people have handed the registrant signed reports: a water taking report from a professional geoscientist or a qualifying professional engineer, and a discharge report from someone with at least a relevant bachelor’s degree.
Source: Ontario Water Resources Act, s.34(1); O. Reg. 387/04, s.4.2(9); O. Reg. 63/16, ss.7–8 (Ontario e-Laws, consolidated text read October 2026)
I’m Arthur Zhao, a real estate broker in Toronto. When an investor asks me about dewatering, the question is almost never about pumps. It is about people. Who is supposed to call the ministry? Whose name goes on the registration? Who gets the phone call if a neighbour’s well drops? Who has to keep the logbook after the contractor has packed up and moved to the next job?
Ontario’s rules answer those questions, but they are spread across a provincial statute, two regulations and a municipal sewer by-law. Read in statute order, they look like a pile of thresholds and exceptions. Read by role, they make much more sense. So that is how this article is laid out: one section for each person or office involved, and what the law expects from each of them.
→
→
→
→
The owner: the threshold, the route, and the exceptions
The starting point is a provincial rule, not a construction rule. Under section 34(1) of the Ontario Water Resources Act, no one may take more than 50,000 litres of water on any day, by any means, except under a Permit to Take Water issued by a ministry Director. Groundwater pumped out of an excavation is a taking of water like any other.
For construction sites there is a second route. Ontario Regulation 63/16 under the Environmental Protection Act lists, as a registrable activity, taking groundwater to create one or more dewatered work areas within a construction site, taking storm water to keep them dry, and the temporary sewage works used only to collect, treat and discharge that water (s.7(1)). A separate water-taking regulation then switches off the permit requirement for activities prescribed this way (O. Reg. 387/04, s.4.2(9)), unless the Director has issued an order about that activity and site. In practice, that means a site that falls inside O. Reg. 63/16 registers on the EASR instead of applying for a permit.
Four things decide whether the owner’s project fits that second route:
- Volume. The registration rules apply only if more than 50,000 litres of groundwater, storm water or both will be taken on at least one day (s.7(2)). Below that line, neither a permit nor a registration is triggered.
- Type of site. A “construction site” for this purpose excludes sites directly associated with mines, pits or quarries (s.6).
- What the water is for. The route does not cover groundwater taken for human consumption, agriculture or an industrial or manufacturing process (s.7(3)), or takings that involve the inter-basin transfers dealt with in sections 34.3 and 34.5 of the Ontario Water Resources Act (s.7(4)).
- Where it goes. If the discharge report recommends discharge to the natural environment inside a wellhead protection area marked “WHPA-A” in an approved source protection plan, the route is closed (s.7(7)).
There is also a transition rule. A project that already held a Permit to Take Water when the 2025 amendment (O. Reg. 66/25) came into force, or had applied for one before that day, keeps going under the permit as long as the permit stays alive or the application is still live (s.7(5.1) and (5.2)).
What the regulation does not do is name the owner as the registrant. It speaks of “a person who proposes to engage in” the activity. Who that person is on your project is a business decision you should make deliberately rather than by default.
⚠️The registration route is not a lighter version of a permit that you can opt into after the fact. Under the Environmental Protection Act, a registrable activity cannot proceed until it is registered and the Director has confirmed the registration, and the two reports have to exist before the registration is filed.
The professional geoscientist or engineer: the water taking report
No registration can be filed until the registrant has received a water taking report (O. Reg. 63/16, s.8(1)(a)). The regulation is specific about who can write it: a practising, temporary or limited member of the Association of Professional Geoscientists of Ontario, or a professional engineer who meets the requirement in paragraph 2 of section 3(3) of the Professional Geoscientists Act, 2000 (s.8(2)). A general contractor’s site supervisor does not qualify by title alone.
For an owner, the useful part is what the report must contain under section 8(4), because it is effectively a list of the risks your neighbours will care about:
- the expected area of influence around each dewatered work area, with the calculations behind it;
- potential sources of contamination in that area and whether pumping could move contaminants;
- soil settlement and land subsidence, including the effect on the integrity of infrastructure within the area of influence;
- the effect on other water users, and on conservation land, fish and wildlife habitat;
- a contingency plan that, if another user’s water supply is affected, provides water equivalent in quantity and quality to their normal takings or compensation for their reasonable cost of getting it, and if necessary reduces the rate of taking;
- a protocol for written notice to potentially affected water users and to the ministry’s district office at least 48 hours before pumping first starts;
- whether a water monitoring plan is needed, and if so, the plan;
- a signed statement that, in the author’s opinion, the taking is unlikely to cause an adverse effect.
If your building sits next to older structures, the settlement paragraph is the one I would read twice. It is the professional’s signed assessment of whether lowering the water table could affect what is next door.
The second author: the discharge report
The registrant also needs a discharge report before registering (s.8(1)(b)). Its author does not have to be a licensed professional, but must hold at least a bachelor’s degree specializing in hydrology, aquatic ecology, limnology, biology, physical geography, or water resources management or engineering (s.8(3)).
This report answers a narrower question: where does the pumped water go, and in what condition? It must assess the quality and quantity of the water and recommend one of four destinations (s.8(5)):
- a waste management system that holds an environmental compliance approval or is itself registered;
- a sewage works;
- a municipal sanitary sewer or storm sewer;
- the natural environment, with treatment and control measures for erosion, flooding, scouring and sedimentation, plus quality controls if contaminant movement is possible.
It also needs its own contingency plan and a view on whether a shutdown protocol is required. Both reports are filed in the Registry with the registration (s.8(6)), so they become part of the project’s registration record, not just internal consultant files.
The contractor with the pumps running: daily duties
Once the registration is in place, section 9.1(2) of O. Reg. 63/16 sets out what has to happen on site. The legal duty sits with the person engaging in the activity; on most sites, the day-to-day work falls to the crew running the pumps:
- Before the first pump starts, run the notification protocol set out in the water taking report.
- Keep both reports available, on paper or electronically, for inspection on request.
- Use the discharge method the discharge report recommends.
- For anything going to the natural environment or a storm sewer, there must be no visible petroleum hydrocarbon film or sheen. Where that discharge point is within 30 metres of a water body, a turbidity limit also applies.
- Operate and maintain the erosion and sediment controls the discharge report calls for, then recover and dispose of them, and whatever they trapped, when the work ends.
- Put the monitoring plans, contingency measures and any shutdown protocol into effect when the circumstances described in the reports arise.
- If a complaint comes in about the taking or the discharge and it relates to the natural environment, notify the ministry immediately.
Section 10 adds the logbook. For each day water is taken, someone must record the average rate in litres per second and the volume in litres for each dewatered work area, along with precipitation on the site, each complaint and how it was handled, proof that the 48-hour notice went out, and the monitoring records.
The City of Toronto: what the sewer side wants
If the discharge report recommends a municipal sewer, a second regulator enters the picture. Toronto’s sewer by-law, Municipal Code Chapter 681, treats groundwater and storm water collected on private land, including water from construction-related activity, as “private water” (§ 681-1).
- Sanitary or combined sewer: discharging private water directly or indirectly is prohibited unless it is under a sanitary discharge agreement or permit with the City that is in good standing, and the discharge meets the concentration limits in the by-law or is covered by an industrial waste surcharge agreement (§ 681-2C).
- Storm sewer: private water is not allowed unless the discharger has first satisfied the General Manager that the other storm sewer requirements are met, and the General Manager has given prior written approval through a discharge agreement or permit (§ 681-4K).
So a provincial registration that names a Toronto sewer as the destination is not, on its own, permission to use that sewer. The City’s agreement or permit is a separate document from a separate office.
There is one more municipal touchpoint, and it comes from the provincial regulation. If the water taking is intended to continue for more than 365 days from the proposed start date, written notice must go to the municipality (upper and lower tier, or single tier) and to any conservation authority with jurisdiction over the site, giving the registrant’s name, the dates, the discharge method and, for natural-environment discharge, its location (O. Reg. 63/16, s.9.1(2) para. 13 and s.9.1(3)).
ℹ️The Toronto by-law text quoted here is from the City’s consolidated Chapter 681 dated May 15, 2023. Consolidations can lag behind amendments, so confirm the current requirements with the City before relying on them. Other Ontario municipalities have their own sewer by-laws; this article only covers Toronto’s.
The Province: what the ministry expects to receive
The Ministry of the Environment, Conservation and Parks sees the project at four points:
- At registration, through the Registry, with both reports filed. Under the Environmental Protection Act, a prescribed activity may only proceed once it is registered, the Director has provided a confirmation of registration, and the registration has not been suspended or removed (s.20.21(1)).
- Before pumping starts, through the 48-hour written notice to the district office.
- Every year by March 31, through a report to the Director setting out the volume of water taken daily for each dewatered work area in the previous calendar year (s.9.1(2) para. 11). The Director may publish water-taking data reported under the regulation (s.10.1).
- At the end: once the taking is no longer needed, notice that the water taking is complete must be filed in the Registry within 30 days after the activity stops (s.9.1(2) para. 14).
And the records do not leave with the pumps. The daily logs, complaint records, notice proofs and monitoring records must be kept for five years from the day each was required to be created, and each water taking report and discharge report for five years from the day it was prepared (s.10).
💡 My own view is that the dewatering file belongs with the land, not with whichever contractor happened to run the pumps. The regulation’s duties outlast construction: the completion notice, five years of daily volume and complaint records, and two signed reports filed in the Registry. If you buy a site where dewatering has already happened, or bring in a new builder halfway through, those documents are part of what you are acquiring. Ask for them by name, and if nobody can produce them, treat that as a finding in your due diligence rather than an administrative gap.
Before you sign, before you pump, after you stop
A short list for owners and investors, sorted by when each item matters.
- ☐Ask whether dewatering is expected and whether any day could exceed 50,000 litres.
- ☐Decide in writing whose name will be on the EASR registration.
- ☐If dewatering already happened, request the confirmation of registration, both reports and the daily records.
- ☐Confirm the water taking report is signed by a P.Geo or qualifying P.Eng.
- ☐Read the settlement and contingency sections of that report.
- ☐Confirm the 48-hour notice to neighbours and the district office has gone out.
- ☐If water goes to a Toronto sewer, confirm the City agreement or permit is in hand.
- ☐Confirm the completion notice was filed in the Registry within 30 days.
- ☐Collect the daily logs, complaint records and both reports, and store them for five years.
- Ontario Water Resources Act, R.S.O. 1990, c. O.40, s.34
- O. Reg. 387/04 (Water Taking and Transfer), s.4.2(9)
- O. Reg. 63/16 (Registrations under Part II.2 of the Act — Water Taking), Part III, ss.6–10
- Environmental Protection Act, R.S.O. 1990, c. E.19, s.20.21
- Toronto Municipal Code, Chapter 681, Sewers (§§ 681-1, 681-2C, 681-4K, 681-6B)
Environmental Compliance Approval: The Operating Permit Most Commercial Buyers Never Ask About →Excess Soil and Commercial Redevelopment in Ontario: The Three Questions That Decide How It Is Regulated →Site Plan Approval: How Commercial Development Drawings Clear Municipal Review in Ontario →Investment Property Guide →
Frequently Asked Questions
I’m buying a lot where the excavation was already pumped out. What should I ask the seller for?
Ask for the EASR confirmation of registration (or the Permit to Take Water), the water taking report, the discharge report, and the daily records of rate and volume. Under O. Reg. 63/16, s.10, those records and both reports must be kept for five years, so they should exist. Also ask whether the completion notice was filed in the Registry within 30 days after pumping stopped.
Only rain and snowmelt collect in my excavation. Do I still have to register?
If more than 50,000 litres could be taken on at least one day, storm-water-only dewatering is exempt from registering, but it is not exempt from the rules (O. Reg. 63/16, ss.7(2) and 9(1)). You still need a discharge report from a qualified author before you start (s.9(2)), and you still have to follow the applicable requirements in s.9.1 and keep the records in s.10.
Our dewatering will run for more than a year. Who else needs to be told?
If the water taking is intended to continue for more than 365 days from the proposed start date, written notice must go to the municipality and to any conservation authority with jurisdiction over the site (O. Reg. 63/16, s.9.1(2) para. 13). The notice includes the registrant’s name, the dates and the discharge method, and the discharge location if water goes to the natural environment.
Can my general contractor write the water taking report?
Only if the author is a practising, temporary or limited member of the Association of Professional Geoscientists of Ontario, or a professional engineer who meets the Professional Geoscientists Act, 2000 requirement (O. Reg. 63/16, s.8(2)). The discharge report can be written by someone with at least a bachelor’s degree in a listed field such as hydrology or water resources engineering (s.8(3)).
What happens if a neighbour complains that our pumping is affecting the environment?
A complaint about the taking or discharge that relates to the natural environment must be reported to the ministry immediately (O. Reg. 63/16, s.9.1(2) para. 12). The date, time, a copy or summary of the complaint and the steps taken must be recorded and kept for five years (s.10). If a neighbour’s water supply is affected, the contingency plan in the water taking report sets out the replacement water or compensation measures.