Building, Pruning or Regrading on a Toronto Ravine Lot: When Chapter 658 Needs a Permit
Your building permit and the City’s ravine permit are separate approvals. On a lot inside the protected area, the second one can decide where the first one’s drawings end up.
Does a building permit cover tree removal and grading on a Toronto ravine-protected lot?
No. Inside a ravine protected area, Toronto Municipal Code Chapter 658 requires its own permit to injure or remove a tree of any species and any size, to place fill, or to alter grade (§658-1, §658-2). The City’s application page says that when a project needs site plan approval or a building permit, the ravine application “will be reviewed with it” and, if approved, issued after site plan approval or “conditional upon a Building Permit being issued.” Even then, §658-6A(3) only authorizes the Executive Director to issue the permit; it is not automatic.
Source: City of Toronto Municipal Code, Chapter 658, Ravine and Natural Feature Protection, §658-1, §658-2, §658-6A(3) (consolidated to September 1, 2026); City of Toronto, How to Apply for a Tree or Ravine Permit
I’m Arthur Zhao with AZ Real Estate Partners. Picture a family with a ravine behind the fence who has finally hired a designer for the rear addition they have talked about for years. The drawings show a bigger kitchen, a deck stepping out toward the slope, and a flatter stretch of lawn where the yard currently tips toward the trees. The plan in their heads is simple: file for the building permit, and the two maples near the edge and the soil work along the bank come along for the ride.
In Toronto that assumption can upend the schedule. Ravine and natural-feature land across the city is mapped as a protected area under Chapter 658 of the Municipal Code, and inside that area the trees, the fill and the grade answer to a separate permit with its own drawings, its own reviewers and its own conditions. Whether your yard is in that area is a fact you can look up before anyone draws a line. So check the map first, then design.
Additions, decks and renovations: two permits, one review
The building permit and the ravine permit are different documents. Chapter 658 defines its own permit as one to injure, destroy or remove trees, place or dump fill or refuse, and alter the grade of land (§658-1), and §658-2 prohibits all of that inside a protected area without one. According to the City of Toronto’s permit application page (2026), this is how the two meet on a construction project: “If your proposed development requires a Site Plan approval or a Building Permit, the Ravine and Natural Feature Permit application will be reviewed with it. If approved, a permit will be issued after the Site Plan approval or it will be issued, conditional upon a Building Permit being issued.”
The by-law wording is permissive, not automatic. Under §658-6A(3), where a building permit has been obtained and tree injury, fill or a grade change is required to build what was approved, the Executive Director is authorized to issue a ravine permit. The review criteria in §658-5.1 include the condition and location of the tree, erosion and flood control, protection of natural landforms and ecological systems, and whether a tree is a distinctive tree. Since September 1, 2026, a distinctive tree is a healthy, non-heritage tree with at least one stem measuring more than 61 cm, measured 1.4 metres above ground (§658-1).
What the ravine package asks for on a construction job (City of Toronto, How to Apply for a Tree or Ravine Permit):
• a plan of survey drawn to scale that shows the limits of the RNFP area;
• a site plan showing existing and proposed buildings and structures, including decks and underground foundation extensions, plus existing and proposed grades;
• an arborist report covering trees on the site and on adjacent properties within 12 metres of any construction activity;
• landscape plans showing every hard-surface element (sidewalks, driveways, fences, retaining walls, steps, decks, patios, swimming pools), with cross-section details for any hard surface proposed inside the protected ravine area of the lot or less than 10 metres from the top-of-bank of the ravine;
• grading plans and a geotechnical report on soil conditions, slope stability, drainage and how the ravine slope will be protected.
Trees you plan to keep are part of this too. Chapter 658 defines “injure” to include not protecting trees in accordance with the City’s Tree Protection Policy and Specifications for Construction Near Trees, and any act or omission that will harm a tree’s health (§658-1). Where an application involves construction, the City’s page says staff require tree protection hoarding to be installed under the approved tree protection plan before the permit is issued.
ℹ️Refused permit: 30 days to appeal. Under §658-8A, if the Executive Director refuses a permit, the applicant may appeal to the community council for the area within 30 days of the date of refusal, by written notice to the Executive Director setting out why the permit should be issued. The City’s application page states that Community Council’s decision is final and cannot be appealed.
Pruning and removing trees
Section 658-2A is short: no person shall injure, destroy or remove, or permit the injury, destruction or removal of, any tree on any land in a protected area unless a permit authorizes it. According to Toronto Municipal Code Chapter 658 (as consolidated in 2026), “tree” means “a tree of any species and any size” (§658-1). That is a different test from the private tree rules elsewhere in the city, where Chapter 813 (§813-12F) turns on a stem diameter measurement of 30 centimetres or more for trees not otherwise covered.
The exceptions in §658-4A, in full. A permit is not required for:
(1) removing a terminally diseased, dead or imminently hazardous tree, certified as such by the Executive Director;
(2) pruning a tree in accordance with good arboricultural practice;
(3) pruning branches that interfere with utility conductors, as certified by the Executive Director;
(4) pruning or removing fruit trees maintained for fruit production;
(5) injuring or destroying a tree in a rooftop garden, interior courtyard or solarium, or on an elevated podium;
(6) emergency work as certified by the Executive Director;
(7) normal maintenance and play enhancement in manicured turf of an existing golf course, as certified by the Executive Director;
(8) farming, maintenance and management in Agricultural Heritage Reserve Zones within the Rouge Park;
(9) maintenance, management or recreational improvements in Special Management Zones within the Rouge Park.
Two details in that list matter to a homeowner. Exception (1) depends on certification by the Executive Director, so a tree you believe is dead or dangerous is not exempt on your say-so alone. Exception (2) relies on “good arboricultural practice,” which §658-1 defines as work done in accordance with ANSI 300 and International Society of Arboriculture best management practices, to the satisfaction of the Executive Director. Pruning that falls outside that standard can still count as injuring a tree.
If a removal permit is granted, §658-6B(1) makes it subject to conditions that the site is restored and replacement trees are planted under the approved plan. Where a tree straddles a property line or sits next door, §658-6G requires the City to give written notice of the application to the co-owners or the neighbour.
Moving soil, adding fill, building garden beds
Section 658-2B prohibits placing or dumping fill or refuse, or altering the grade of land, in a protected area without a permit. “Fill” covers earth, sand, gravel, rubble and similar material “whether originating on the site or elsewhere” that is used or capable of being used to change the contours of the ground (§658-1). Moving your own topsoil from the front of the lot to the back is not outside the definition just because it never left the property.
The exceptions in §658-4B, in full. A permit is not required for:
(1) cultivating or tilling garden beds, as long as the work does not alter or create slopes at greater than 10 percent;
(2) placing less than five cubic metres of soil to maintain existing manicured areas;
(3) placing fill or refuse, or altering grade, on rooftop gardens or in interior courtyards, solariums, raised podiums or planters;
(4) emergency work as certified by the Executive Director;
(5) grade changes within areas regulated by the Toronto and Region Conservation Authority;
(6) normal maintenance and play enhancement in manicured turf of an existing golf course, as certified by the Executive Director;
(7) farming, maintenance and management in Agricultural Heritage Reserve Zones within the Rouge Park;
(8) maintenance, management or recreational improvements in Special Management Zones within the Rouge Park;
(9) erecting a fence that complies with the applicable zoning or fence by-law, provided the uphill side is kept clear of refuse and fill.
Note how narrow exception (2) is: it is tied to existing manicured areas, not to building up a new terrace or levelling a slope. Where a permit is needed, the application has to include a grading plan showing existing and proposed conditions, a drainage plan and a geotechnical report (§658-5B(4)).
Same yard, different answer
When the lot is also in the TRCA’s regulated area
Some ravine lots sit inside both the City’s protected area and an area regulated by the Toronto and Region Conservation Authority. Chapter 658’s list of exemptions deals with that overlap in one place only: §658-4B(5) exempts grade changes within TRCA-regulated areas from the Chapter 658 permit. The tree exceptions in §658-4A contain no TRCA item, so injuring or removing a tree on the same lot still needs the City’s ravine permit. Section 658-6A(7) points the same way from the other side: it authorizes the Executive Director to issue permits for fill or grade changes that are outside the TRCA’s regulated area and in line with approved plans.
What the TRCA itself requires is outside the scope of this article, and I have not reviewed its rules here. If your property may be in its regulated area, confirm directly with the TRCA what approvals it needs before you finalize grading, and keep the City’s tree permit on your list either way.
💡 My own judgement is this: look up the Schedule A-2 map before you settle on a design. Chapter 658 does not care how big the project is; it cares whether the work lands in the shaded area. If it does, the ravine permit, with its survey, arborist report, grading plans and geotechnical report, sits on the critical path alongside the building permit. Knowing that on day one lets you and your designer decide where the deck, the footings and the regraded lawn go while those choices are still cheap to change.
If the work has already been done
Chapter 658 gives the City several tools once work has happened without a permit or outside a permit’s conditions.
• Inspection. An employee or officer of the City may enter any lands at any reasonable time to check compliance with the chapter or a permit, require documents and information, and take tests, samples and photographs. Contravention inspection fees under Chapter 441 can apply (§658-9).
• Orders. An officer can order the activity discontinued and order work done to correct the contravention (§658-10A). If the occupant is not the registered owner, both are served; where service is not possible, a placard on the property counts as service, and no one may deface, cover or remove it (§658-10C to E).
• Restoration. Whoever injured or destroyed a tree, placed fill or altered grade without a permit, or against a permit condition, must replace the tree, remove the fill, regrade and restore the site to its original condition to the Executive Director’s satisfaction (§658-11).
• Fines. A contravention of any provision is an offence (§658-12A). Fill and grade offences under §658-2B, and failing to comply with permit conditions, are continuing offences with a minimum fine of $500 and a maximum of $10,000 for each day or part of a day they continue (§658-12D, E).
• City does the work. If a required step is not done, it can be done under the Executive Director’s direction and the costs recovered by action or added to the tax roll and collected like property taxes (§658-13).
If you receive an order or a charge, speak with a lawyer or licensed paralegal about your specific situation.
⚠️Tree fines are counted tree by tree. Under §658-12C(1), a person convicted is liable “to a minimum fine of $500 per tree and a maximum fine of $100,000 for the injury or destruction of any tree in a protected area.” Section 658-12C(3) adds a special fine of $100,000, and §658-12B makes a director or officer of a corporation who knowingly concurs in a contravention guilty of an offence.
Checklist for a ravine-lot project
- ☐Check whether any part of the lot falls in a shaded area on the Chapter 658 Schedule A-2 Data Maps.
- ☐Get a plan of survey that shows the limits of the RNFP area, and give it to your designer.
- ☐Ask an arborist to inventory trees on your lot and on neighbouring lots within 12 metres of the planned construction.
- ☐Flag any deck, patio, wall or other hard surface inside the protected area or less than 10 metres from top-of-bank; it will need cross-section details.
- ☐Ask a geotechnical professional about slope stability before you commit to any regrading near the bank.
- ☐Confirm the Chapter 658 permit has actually been issued, not just the building permit.
- ☐Install tree protection hoarding as the approved tree protection plan requires.
- ☐Post the permit where it is visible from the street for one day before work begins, and leave it up until the permitted work is finished (§658-6F).
- ☐Walk your contractor through the permit conditions and the approved plans.
- ☐Keep work within the approved plans; ask City staff before touching any tree not in the permit (§658-6E).
- ☐Keep surplus soil and debris off the slope and out of the protected area.
- ☐Keep the permit and approved drawings on site so you can produce them on request.
- ☐Provide the documents and information the officer asks for during an inspection (§658-9B).
- ☐Read any order closely for what must stop and what must be corrected (§658-10A).
- ☐Leave any placard in place; removing or covering it is prohibited (§658-10E).
Ontario Tree By-laws: Why Cutting Down a Tree on Your Own Property Can Require a Permit →Conservation Authority Permits: Building Near Ontario’s Regulated Lands →The House You Love Is in a Flood Zone or by a River — Can You Still Buy It? →First-Time Renter Guide →
Frequently Asked Questions
How do I find out whether my lot is in the ravine protection area?
Chapter 658 defines the protected area as a shaded area on any Data Map in Schedule A-2 of the chapter (§658-1). The City’s application page links to a lookup for whether a property is regulated under the Ravine and Natural Feature Protection By-law, notes that the RNFP line can be downloaded free online for your plans, and says the City can mark the line on a survey for a fee. If you are unsure, the page directs you to 311 or your local Tree Protection and Plan Review office.
Can I prune trees in a ravine protection area without a permit?
Yes, if the pruning follows good arboricultural practice (§658-4A(2)), which Chapter 658 defines as work in accordance with ANSI 300 and International Society of Arboriculture best management practices, to the satisfaction of the Executive Director. Pruning outside that standard can count as injuring the tree, which needs a permit under §658-2A. Root pruning is listed separately in §658-6A(4) as something the Executive Director may permit under the direction of an approved arborist.
Does a TRCA permit replace the City’s ravine permit?
Not across the board. Chapter 658 exempts only grade changes within TRCA-regulated areas from the City permit (§658-4B(5)); the tree exceptions in §658-4A have no TRCA item, so tree injury or removal still needs the City’s permit. Confirm the TRCA’s own requirements with the TRCA directly.
Can my contractor apply for the permit on my behalf?
Chapter 658 defines the applicant as the registered owner of the property or the registered owner’s authorized agent (§658-1), so an authorized agent can file. The owner still carries exposure: §658-2 prohibits anyone from injuring trees or altering grade, or permitting it, without a permit, and §658-12A makes any contravention an offence.
Do I need a permit to plant a vegetable garden on the slope?
Cultivating or tilling garden beds is exempt as long as the work does not alter or create slopes at greater than 10 percent (§658-4B(1)). Terracing the slope or building it up with soil is a grade change or placing fill, which needs a permit unless another exception applies; the soil exception in §658-4B(2) covers less than five cubic metres for maintaining existing manicured areas only.