Tax, Legal & TRESA · Oct 18, 2026 · 13 min read
📖 Tax, Legal & TRESA

The Estimate, the Change Order, the Final Bill: How Ontario’s 10% Rule Reads Your Renovation Paperwork

When a contractor texts that the job will cost more, the Consumer Protection Act already has a view on it. Which of your three pieces of paper exists decides how much of that view you can use.

Arthur Zhao · Broker · AZ Real Estate Partners · 2026-10-18
Quick Answer

If my contractor’s bill comes in well above the estimate, what does Ontario law actually say?

The Act puts a duty on the contractor and hands a matching right to you. The duty: if a consumer agreement includes an estimate, the supplier “shall not charge the consumer an amount that exceeds the estimate by more than 10 per cent” (Consumer Protection Act, 2002, s.10(1)). The right: if the supplier does charge more than that, you “may require that the supplier provide the goods or services at the estimated price” (s.10(2)), which is the estimate itself, not the estimate plus 10%. The one opening for a higher price is s.10(3): you and the supplier may agree to amend the estimate or price if you require additional or different goods or services.

Source: Consumer Protection Act, 2002, S.O. 2002, c. 30, Sched. A, ss. 10(1)–(3), e-Laws consolidation from December 11, 2025

Halfway through a bathroom job, the message arrives on your phone: “the vanity you picked is back-ordered, the one in stock costs more, OK?” No number. No paperwork. Just a heads-up and an expectation that you will say OK so the crew can keep going.

I’m Arthur Zhao, a real estate broker in Toronto. When a homeowner shows me a message like that, my first question is not “how much more?” It is “show me the paper.” Ontario’s Consumer Protection Act, 2002 has a specific rule for bills that overshoot an estimate, but the rule works through documents: the estimate you started with, whatever you agreed to when the work changed, and the invoice at the end. This piece takes those three pieces of paper one at a time: what each one is in the statute, what the statute makes it carry, and what happens when it is missing.

Paper 1: the estimate sets the number s.10 measures against

→

Paper 2: the change order (or the text reply) is the only route to a new number under s.10(3)

→

Paper 3: the final invoice is where s.10(1) is tested and s.10(2) can be used

Paper 1: the estimate

What it is in the statute. Section 10 switches on when “a consumer agreement includes an estimate.” Part II of the Act, where s.10 sits, does not define “estimate.” The Act does define the word in s.55, but only “in this Part,” meaning Part VI, which deals with repairs to motor vehicles and other goods and describes an estimate of “the goods being repaired.” That definition is not built for a kitchen or a bathroom, so I would not borrow it.

The estimate also has to sit inside a consumer agreement between a consumer and a supplier. Section 1 defines a consumer as “an individual acting for personal, family or household purposes,” and says the term “does not include a person who is acting for business purposes.” A supplier is “a person who is in the business of … supplying goods or services.” Section 2(2)(f) takes purchases, sales and leases of real property outside the Act, but s.2(6) adds that, despite (2)(f), the Act applies where a supplier supplies goods that are not part of the real property when the agreement is made but become part of it under the agreement. My reading, and it is an inference rather than a ruling, is that hiring someone to renovate the home you live in is a services contract, not a purchase or sale of the house, so (2)(f) does not take it out of the Act.

What the statute makes it carry. The estimate is the baseline. Every later number gets measured against it. Take a hypothetical: an estimate of $18,000 puts the s.10(1) ceiling at $19,800. A bill of $21,500 is past that line, and s.10(2) then lets you require the work at the estimated price, $18,000.

What happens if it is missing. If no estimate was ever given, s.10 has nothing to measure against. If one was given but is vague (“bathroom, about eighteen”), s.11 helps a little: any ambiguity in a consumer agreement the supplier provided that allows more than one reasonable interpretation “shall be interpreted to the benefit of the consumer.” Section 7(1) adds that the Act’s rights apply “despite any agreement or waiver to the contrary,” so a line in the contract saying the estimate can be exceeded without limit does not, on the text, switch s.10 off.

If the contractor sat at your kitchen table to sign you up, there is a second layer. Section 20 defines a direct agreement as a consumer agreement negotiated or concluded in person somewhere other than the supplier’s place of business (or a market, auction, trade fair, agricultural fair or exhibition). Where your total potential payments exceed $50 (s.41(1) with O. Reg. 17/05, s.34), s.42(1) requires the agreement to be in writing and delivered to you, and O. Reg. 17/05, s.35(1) lists what it must set out, including a fair and accurate description of the goods and services, the total amount payable, and an itemized list of prices. A direct agreement also carries a 10-day cancellation right under s.43(1); the cooling-off rules have their own article, linked under related reading below.

💡 My own view: nothing in s.10 says an estimate has to be in writing, and outside the direct-agreement rules the Act does not make the contractor put one on paper. That cuts both ways. A verbal estimate can still count, but a verbal estimate is also the hardest one to prove when the bill arrives. Because the statute will not make anyone write it down, writing it down is your job: an email back to the contractor that repeats the number, the scope and the date takes two minutes and turns a memory into a baseline.

Paper 2: the change order, or the text message that stands in for one

What it is in the statute. Section 10(3) is the one place the Act lets the number move: “Nothing in this section prevents a consumer and a supplier from agreeing to amend the estimate or price in a consumer agreement, if the consumer requires additional or different goods or services.” Two conditions are packed into that sentence. There has to be an agreement to amend, and the trigger is that the consumer requires additional or different work.

What the statute makes it carry. Whatever you agree to mid-job becomes the new reference point. That is why the reply to “the vanity you picked is back-ordered, the one in stock costs more, OK?” matters. The Act’s text does not mention substitutions the contractor proposes; it speaks of you requiring something additional or different. Whether a one-word “OK” to an open-ended message amounts to agreeing to an amended price, and at what amount, is not something the wording of s.10(3) settles on its own. A reply that names the extra work and a number leaves far less to argue about.

Section 10 does not say the amendment has to be in writing. If the original contract was a direct agreement, s.42(1) required that agreement to be in writing; the Act’s text, as I read it, does not separately say whether a later amendment counts as a new direct agreement, so I would not rely on either answer without advice.

What happens if it is missing. If there is no record of an agreed change, the final bill has to be compared with the original estimate alone, and the conversation turns into your recollection against the contractor’s. If there is a record that is unclear, s.11 again reads ambiguity in a supplier-provided agreement in your favour, but only to the extent the document is genuinely open to more than one reasonable reading.

⚠️Section 10(3) only lets the price move by agreement, tied to additional or different work you require. A contractor announcing that the job “will be more” is not, on the text of the section, an agreement on its own.

Paper 3: the final invoice

What it is in the statute. The invoice is the “charge” that s.10(1) regulates. It is where the rule is tested: the amount charged against the estimate, as amended under s.10(3) for any extra or different work you required.

What the statute makes it carry. If the charge exceeds the estimate by more than 10 per cent, s.10(2) gives you the right to require the work at the estimated price. Separately from price, s.9(1) deems the supplier to warrant that services supplied under a consumer agreement “are of a reasonably acceptable quality,” so an invoice for work that falls short of that standard raises a second, independent issue.

If the contractor will not move, the Act names two routes. Section 100(1): where a consumer has a right to commence an action under the Act, the consumer “may commence the action in the Superior Court of Justice.” Section 105(1): the Ministry may receive complaints about conduct that may contravene the Act and may “make inquiries, gather information and attempt to mediate or resolve complaints.” According to the Government of Ontario’s “Filing a consumer complaint” page (updated December 5, 2025), home renovation and maintenance is one of the complaint types it can assist with, the Ministry recommends writing to the business first, and it says it will contact you within 15 business days of a complaint.

What happens if it is missing. An invoice with one lump sum and no breakdown makes the comparison with the estimate and any change order harder to do line by line. Ask for the breakdown before you pay the balance, not after.

Which Act you are reading today

The rules above come from the Consumer Protection Act, 2002, which is the law in force. Ontario has passed a replacement, the Consumer Protection Act, 2023, but e-Laws carries this note at the top of it: “THIS ACT IS NOT YET IN FORCE. It comes into force on a day to be named by proclamation of the Lieutenant Governor.” The 2002 Act carries the matching note that it “is repealed on a day to be named by proclamation.” The estimate rule survives the rewrite: s.12(1) of the 2023 Act says that if a consumer contract includes an estimate, the supplier shall not charge more than the estimate “by more than 10 per cent,” and s.12(2) and (3) repeat the estimated-price right and the additional-or-different-work exception. I am not going to guess when the new Act will be proclaimed; there is no official date to cite.

Three papers, checked before the last payment

Work through these by document, not by date. If one of the three papers does not exist yet, the items under it tell you what to create.

The estimate
  • ☐Find the number, the scope it covers and the date it was given, in whatever form it exists: contract, email, text or quote sheet.
  • ☐Confirm it in writing if it was only spoken, by replying to the contractor with the amount and scope.
  • ☐Work out the s.10(1) line: the estimate plus 10 per cent.
  • ☐Check whether you signed at home; if so, look for the written copy and the items O. Reg. 17/05, s.35(1) requires, such as the total amount payable and an itemized price list.
The change order or the mid-job message
  • ☐Collect every message where the scope or price changed, including your own replies.
  • ☐Note for each change whether you asked for the extra or different work, and whether a price was stated.
  • ☐Reply to any open-ended “it’ll be more” message with a request for the amount before work continues.
The final invoice
  • ☐Ask for a breakdown that separates original scope from each agreed change.
  • ☐Compare the original-scope portion against the estimate and the 10 per cent line.
  • ☐Write to the contractor first, naming s.10 and the amounts, and keep a copy.
  • ☐File with the Ministry through Consumer Protection Ontario if the business does not resolve it, attaching the estimate, messages and invoice.

Frequently Asked Questions

Q

My contractor calls it a quote, or says the number was just a ballpark. Does the 10% rule still apply?

A

Section 10(1) of the Consumer Protection Act, 2002 applies when a consumer agreement “includes an estimate,” and Part II of the Act does not define “estimate,” “quote” or “ballpark.” The only statutory definition of estimate, in s.55, is limited to Part VI repairs to vehicles and other goods. The Act does not say that a label changes the result, and s.11 reads genuine ambiguity in a supplier-provided agreement in the consumer’s favour; beyond that, how a particular number is characterized is a question for advice on your own documents.

Q

I own a rental property and I’m renovating a unit. Am I a “consumer” under the Act?

A

Section 1 of the Consumer Protection Act, 2002 defines a consumer as an individual acting for personal, family or household purposes, and says it “does not include a person who is acting for business purposes.” The definition points toward asking whether you signed the renovation contract as part of a rental business. The Act does not list landlords one way or the other, so confirm your position before relying on s.10.

Q

I agreed to the extra work verbally. Does that change count under s.10(3)?

A

Section 10(3) allows a consumer and supplier to agree to amend the estimate or price when the consumer requires additional or different goods or services, and it does not say the agreement must be in writing. A separate rule, s.42(1), requires a direct agreement (one negotiated or concluded in person away from the supplier’s place of business, over $50 under O. Reg. 17/05, s.34) to be in writing. The practical problem with a verbal change is proof of what was agreed and at what price.

Q

The Act says I can sue in the Superior Court of Justice. Where do I actually start?

A

Section 100(1) of the Consumer Protection Act, 2002 says that if a consumer has a right to commence an action under the Act, the consumer may commence it in the Superior Court of Justice. That is what the section states; it does not by itself tell you which court office or procedure fits your claim. Get legal advice on the forum and the amount before filing.

Q

What can the Ministry actually do with my complaint about a contractor?

A

Under s.105(1) of the Consumer Protection Act, 2002, the Ministry may receive complaints about conduct that may contravene the Act and may make inquiries, gather information and attempt to mediate or resolve them. The Government of Ontario’s complaint page (updated December 5, 2025) says it will contact you within 15 business days, and that it may not be able to help with events more than two years old or with compensation other than a refund of money paid or cancellation of an agreement. Consumer Protection Ontario’s toll-free number on that page is 1-800-889-9768.


Discover more from GTA Real Estate Broker | Arthur Zhao

Subscribe to get the latest posts sent to your email.

Continue reading

相关文章Related articles

Tax, Legal & TRESA

装修最后的账单比报价高出一大截?安省消费者保护法的估价规则

装修完工,账单比报价高出一大截,屋主该怎么办?安省《Consumer Protection Act, 2002》s.10 规定:含估价的消费者协议,商家收费不得超过估价 10% 以上;超过了,消费者可要求按估价价格提供服务;但消费者自己要求的加项改项,双方可另行修改价格。本文逐条讲清谁算 consumer、哪些交易被排除、在家签的装修合同为何要书面、估价写不清时 s.11 如何有利于消费者、s.9 的服务质量保证,以及投诉与起诉渠道。2023 年新法已通过但尚未生效,10% 规则在新法 s.12 原样保留。

Oct 18, 2026
Tax, Legal & TRESA

Marriage Contracts and Cohabitation Agreements: What They Can and Can’t Do for Your Home in Ontario

Owning a home before the wedding, signing after you marry, living together with no plan to marry, or marrying after a cohabitation agreement: what Ontario’s Family Law Act lets a domestic contract settle about the house in each case, and what it will not enforce.

Oct 17, 2026
Tax, Legal & TRESA

婚前协议与同居协议:能怎样保护你的房子,哪些条款写了也无效

婚前协议(marriage contract)能约定房子的价值不计入 net family property(FLA s.4(2)¶6),但限制配偶在婚姻住宅居住、免除卖房抵押需配偶同意的条款,按 FLA s.52(2) 不可执行;能放弃这些权利的是分居协议(s.21(1)(b))。未婚同居伴侣不适用财产均分和婚姻住宅规则,同居协议的作用是约定产权与分割;结婚后同居协议视为婚前协议(s.53(2))。协议须书面、签字、见证(s.55(1)),隐瞒重大资产可被撤销(s.56(4))。

Oct 17, 2026
您好!想了解房产买卖、投资、贷款?随时问我。 点这里开聊 →
Arthur Zhao

AZ 房产 AI 顾问

Arthur Zhao · Real Estate Broker

选个话题快速开始
Powered by AZ Real Estate Partners · 对话用于改进服务

Discover more from GTA Real Estate Broker | Arthur Zhao

Subscribe now to keep reading and get access to the full archive.

Continue reading