Interim Control By-laws in Ontario: What a Development Freeze Protects, Depending on Who You Are
The same by-law reads very differently to an owner-operator, a landlord, a developer and a buyer still in the conditional period. Here is where each one stands.
What kind of tool is an interim control by-law, and who is allowed to pass one?
It is a temporary land use prohibition passed under section 38 of Ontario’s Planning Act. Only the council of a local municipality can pass one, and only after council has directed, by by-law or resolution, that a review or study of its land use planning policies be undertaken. The by-law can prohibit using land, buildings or structures in a defined area for the purposes it lists (or for anything except the purposes it lists). It is capped at one year from passing, extendable to a two-year total, and no notice or hearing is required before council passes it.
Source: Planning Act, R.S.O. 1990, c. P.13, s. 38(1)–(3) (Ontario e-Laws, consolidation from July 1, 2026)
I’m Arthur Zhao, a real estate broker in Toronto. Here is the kind of call that puts this topic on the table. A plaza owner has finally lined up a tenant for the empty end unit. The tenant’s broker phones back a week later: the city has passed an interim control by-law covering the area, and the use the tenant wants is on its list. The owner never got a letter. Nobody at city hall asked for his opinion beforehand.
Both of those things can be perfectly normal. An interim control by-law is designed to be passed first and explained afterward, so the city can pause certain uses while it studies its planning rules. What makes it confusing is that its effect depends almost entirely on what you were already doing with the property on the day it passed.
So instead of walking through the by-law clause by clause, this piece sorts it by who you are: an owner running your own business on the site, a landlord with tenants trading there, an owner with permit or planning files in progress, and a buyer who has signed but not yet closed. For each, what the statute protects, what it leaves exposed, and the questions worth asking. This explains how the rules are written; it is not legal advice for your property.
The tool in brief: what it can do and how it ends
According to the Planning Act (s.38), an interim control by-law is about use: it prohibits land, buildings or structures in the defined area from being used for the purposes it names, or for anything other than the purposes it names. It does not by itself rezone your property. It holds things still while council finishes the review or study it directed.
- Length. Up to one year from passing (s.38(1)); council can amend it to extend, but the total cannot exceed two years from the original passing (s.38(2)).
- How it ends. If it expires and council has not passed a new zoning by-law under s.34 arising from the study, or if it is repealed or its area is reduced, the zoning that applied before it comes back into effect for the affected lands (s.38(6)). If council did pass a new s.34 by-law in time but that by-law is under appeal, the interim control by-law stays in effect until the Ontario Land Tribunal’s order (s.38(6.1)).
- No immediate repeat. Once it stops being in effect, council cannot pass another interim control by-law on any of the same lands for three years (s.38(7)).
- Notice comes after, not before. The clerk must give notice within 20 days of passing, in the manner and to the persons the regulations prescribe (s.38(3)).
- Appeal window. A person or public body that was given notice may appeal to the Tribunal within 50 days after the date the by-law was passed (s.38(4), in force June 8, 2023). By-laws passed before the Helping Homebuyers, Protecting Tenants Act, 2023 received Royal Assent continue under the section as it read before (s.38(4.1)).
Notice that the appeal clock runs from the date of passing, not from the day you happen to find out.
⚠️No letter does not mean no by-law. The regulation lets a municipality give notice by newspaper (or, where there is no suitable newspaper, on its website) instead of mailing nearby owners. If you own or are buying commercial property in an area under review, ask the municipality directly rather than waiting for mail.
The two carve-outs everything below depends on
Section 38(8) applies s.34(9) of the Planning Act to interim control by-laws. That subsection says a by-law does not apply:
- (a) to an existing lawful use: land, a building or a structure that was lawfully used for a purpose on the day the by-law was passed can keep being used for that purpose, so long as it continues to be used for that purpose;
- (b) to a building with an already-issued permit: a building or structure for which a permit was issued under s.8(1) of the Building Code Act, 1992 before the day of passing can be erected and used for the purpose it was erected for, as long as it continues to be used for that purpose and the permit has not been revoked under s.8(10) of that Act.
Everything that follows comes back to these two sentences. Notice what they reward: something lawfully happening on the ground, or a permit already in hand, on a specific date. Intentions, drawings and pending files are not mentioned.
💡 My own view: with an interim control by-law, the most useful asset you can hold is proof of where you stood on the day it was passed. A running, lawful use and an issued permit are what the statute protects; plans and applications are not. Whatever your role, the first document worth finding is the one that shows your position on that date.
Four owners, one by-law
Each of the four sections below follows the same pattern: what the statute protects for you, what it leaves exposed, and the questions to bring to the municipality and your lawyer.
1. You own the site and run your own business on it
Protected. If your business was a lawful use of the property on the day of passing, s.34(9)(a) lets you keep using the property for that purpose while the by-law is in effect. The key word is lawfully: the carve-out covers a use that was lawful, not simply one that existed.
Exposed.
- Switching uses. The protection is tied to continuing that purpose. Moving into a use the by-law prohibits is not covered.
- Growing. The carve-out speaks about continuing a use. It says nothing about enlarging it.
- Building work that needs a permit. Under the Building Code Act s.8(2)(a), the chief building official does not issue a permit where the proposed work will contravene the Act, the building code or any other applicable law. For a conditional permit, s.8(3)(a) is explicit: compliance with by-laws passed under sections 34 and 38 of the Planning Act must already have been achieved.
Questions to ask.
- Does my current use fall within the purposes the by-law lists, or outside them?
- Was my current use lawful under the zoning that applied on the day of passing, and what records show that?
- If I need to renovate, how is the building department treating this by-law for permits on my site?
2. You are a landlord with tenants trading on the property
Protected. Section 34(9)(a) is written in terms of the land, building or structure and how it is used. If a tenant’s business was a lawful use on the day of passing, that use can carry on for as long as the space continues to be used for that purpose.
Exposed.
- Vacancies. The protection lasts “so long as it continues to be used for that purpose.” The statute does not say how long a unit can sit empty before that continuity is broken. If a protected tenant leaves, that is a question for your lawyer before you re-let, not after.
- A different use in the same unit. A new tenant with a use the by-law prohibits does not inherit the old tenant’s protection, because the carve-out is tied to continuing the same purpose.
- A new operator, same use. The text does not mention who operates the business. Whether a change of operator matters on your facts, especially with a gap in between, is not something s.34(9) answers directly.
- Tenant fit-outs. Your tenant’s permit applications face the same Building Code Act test described above.
Questions to ask.
- Which of my units hold uses the by-law lists, and what evidence do I have of each use on the day of passing?
- What do my leases say about permitted use, and what happens under them if a tenant cannot get a permit it needs?
- Before I sign a replacement tenant, does the proposed use survive the by-law on its own terms?
3. You have permit or planning applications in progress
Protected. Only one stage of your file gets an express carve-out: a building permit issued under Building Code Act s.8(1) before the day of passing. Under s.34(9)(b), the building can be erected and used for its intended purpose, provided it continues to be used for that purpose and the permit is not revoked under s.8(10).
Exposed.
- A permit that was applied for but not yet issued. Section 34(9)(b) refers to a permit that has been issued. An application in the queue on the day of passing is not described.
- Revocation risk on an issued permit. The protection depends on the permit not being revoked. Building Code Act s.8(10) lets the chief building official revoke a permit on listed grounds, including where construction has not been seriously commenced six months after issuance, or has been substantially suspended or discontinued for more than one year, in the official’s opinion.
- Rezoning and site plan files. Section 38 itself says nothing about planning applications already in process. The end point it does describe is either a new s.34 zoning by-law that comes out of the study, or a return to the prior zoning (s.38(6)).
Appeal. A person or public body that was given notice may appeal within 50 days after passing (s.38(4)). Where notice is given other than by newspaper publication, O. Reg. 545/06 s.9(8) requires it to state that only individuals, corporations and public bodies may appeal, and that an unincorporated association or group may not, although a member may file in their own name on the group’s behalf.
Questions to ask.
- Exactly what was issued, and when, relative to the date the by-law was passed?
- Is my construction schedule exposed to any of the s.8(10) revocation grounds while the by-law is in effect?
- How is the city handling applications like mine during the study, and what is the study looking at in my area?
- Do I want to appeal, and is the 50-day window from passing still open?
4. You have signed to buy, and you are still in the conditional period
Protected. If the seller’s current use was lawful on the day of passing, s.34(9)(a) is written around the property and its use, not around the owner’s name. Similarly, a permit issued before passing is attached to a building under s.34(9)(b). Whether those protections carry through your purchase on your specific facts, particularly if the use is interrupted around closing, is a question for your lawyer.
Exposed.
- Your plan for the property. If you are buying to introduce a use the by-law prohibits, or to redevelop, nothing in s.34(9) covers you. Those plans are exactly what the by-law can pause.
- Hearing about it. According to O. Reg. 545/06 s.9, the municipality gives notice in one of three ways: in a newspaper with sufficiently general local circulation, on its website if no such newspaper exists, or by personal service or ordinary mail to every owner within 120 metres of the subject land. Mailed notice goes to the owner on the last revised assessment roll, which is the seller, not you. You may never see a notice addressed to you.
- Timing. The 50-day appeal window under s.38(4) runs from the date of passing. A buyer who learns of the by-law weeks later may find much of it gone.
Questions to ask.
- Is any interim control by-law in effect on this property, and on what date was it passed?
- Has council directed a land use review or study for this area? (Under s.38(1), that direction must come before any interim control by-law.)
- Did the seller receive any notice, and what was the property actually being used for on the day of passing?
- Do my conditions, and the time left on them, give me room to get these answers?
Who to ask, and what to ask them
Organised by the person you need to reach, since most of the answers sit in someone else’s files.
- ☐Pull leases, invoices and other records that show what the property was used for on the day the by-law was passed.
- ☐Find the date of any building permit issued for the property and compare it with the by-law’s passing date.
- ☐Check whether any notice of the by-law was received at the property or by the registered owner.
- ☐Ask for a copy of any interim control by-law that covers the property, with its passing date and any extension.
- ☐Ask whether council has directed a land use review or study for the area, and what it covers.
- ☐Ask how the building department is treating the by-law for permit applications on the site.
- ☐Confirm whether your current use falls inside the s.34(9)(a) carve-out on your facts.
- ☐Review lease use clauses, or your purchase conditions, against the by-law.
- ☐If an appeal is on the table, confirm whether you were given notice and that the 50-day window from passing is still open.
- Planning Act, R.S.O. 1990, c. P.13, s. 38 (interim control by-laws) and s. 34(9) (Ontario e-Laws, consolidation from July 1, 2026)
- Building Code Act, 1992, S.O. 1992, c. 23, s. 8 (building permits, conditional permits, revocation) (Ontario e-Laws, consolidation from June 2, 2026)
- O. Reg. 545/06, Zoning By-laws, Holding By-laws and Interim Control By-laws, s. 9 (notice of passing) (Ontario e-Laws, consolidation from June 30, 2026)
Zoning By-law Amendment: How to Rezone Commercial Land for a Use That Isn’t Currently Permitted →Legal Non-Conforming Use: Can You Buy a Home That Doesn’t Meet Zoning? →Site Plan Approval: How Commercial Development Drawings Clear Municipal Review in Ontario →First-Time Renter Guide →
Frequently Asked Questions
Does an interim control by-law mean my property is going to be rezoned?
Not necessarily. Under Planning Act s.38(6), if the by-law expires and council has not passed a new zoning by-law under s.34 arising from its study, or if the by-law is repealed, the zoning that applied before comes back into effect. The by-law pauses listed uses while the study runs; the study’s result is what decides any rezoning.
Can I still sell a commercial property that is under an interim control by-law?
Section 38 of the Planning Act is written in terms of the use of land, buildings and structures; it does not mention sales or transfers. What the by-law affects is what a buyer can do with the property, so expect a buyer to ask what the current use is and whether it was lawful on the day of passing, since that is what s.34(9)(a) protects.
Can our business association file one appeal on behalf of all the owners in the area?
Not in its own name if it is unincorporated. Under O. Reg. 545/06 s.9(8), every notice other than a newspaper notice must state that only individuals, corporations and public bodies may appeal an interim control by-law to the Ontario Land Tribunal, and that a member may file in their own name on the group’s behalf. The appeal must be filed within 50 days after the by-law was passed (Planning Act s.38(4)).
Does an interim control by-law stop every kind of business in the area?
No. Under Planning Act s.38(1), the by-law prohibits the uses it sets out, or everything except the uses it sets out, within the area it defines. Two by-laws can therefore reach very different businesses, so the by-law’s own list is the thing to read, together with the s.34(9) carve-out for uses that were lawful on the day it passed.
Discover more from GTA Real Estate Broker | Arthur Zhao
Subscribe to get the latest posts sent to your email.