Construction & Self-Build Mortgages in Ontario: How Progress-Draw Financing Actually Works

Buying land to build, tearing down and rebuilding, or adding a major addition isn’t financed with a normal mortgage — it’s a draw mortgage that releases money in stages, and the cash flow rules surprise almost everyone.

Arthur Zhao · Broker · AZ Real Estate Partners · 2026-07-08
Quick Answer

How do you finance building your own home or a tear-down rebuild in Ontario?

A custom build, tear-down rebuild, or major addition is financed with a construction (draw) mortgage: instead of one lump sum, the lender releases funds in stages (“draws”) as the build hits milestones, inspects the work before each draw, and you pay interest only on the money advanced so far during construction — then it converts to a normal amortizing mortgage once the home is finished. Source: RBC Royal Bank (2026) and CMHC (2026).

Sources: RBC Royal Bank (rbcroyalbank.com, 2026); CMHC (cmhc-schl.gc.ca, 2026); Ontario Construction Act, s. 22 (ontario.ca, 2026)

I’m Arthur Zhao. More of my GTA clients now buy a lot to build, or tear down an older house and rebuild, than a few years ago. The first thing they say is usually “the mortgage is basically the same, right?” It isn’t. A construction mortgage is a different product: money comes in stages, each stage is inspected before funding, you pay interest-only while you build, and a holdback comes off every draw. Miss how this works and you get squeezed at the foundation and framing stage. Here’s the plain version.

Land / lot draw (~65% of land)

→

Foundation complete → inspect → fund

→

Framing / lock-up draw

→

Systems & exterior draw

→

100% complete → final draw → convert

First, know which model you’re in: draw vs completion

There are two models. A draw (progress-advance) mortgage releases money in stages as the build hits milestones; you pay interest only on what’s been drawn. Custom builds, tear-down rebuilds and smaller builders almost always use this. A completion mortgage is arranged in advance but funds only on possession — the builder carries construction costs and you pay no interest during the build; big production builders use this. GTA self-builds and rebuilds are almost always the draw model. Source: Sterling Homes / NerdWallet Canada (2026).

1

First draw: the land, capped around 65%

Using RBC’s typical five-draw, one-year schedule: the first draw is for the land, released up to about 65% of the lot’s appraised value — the maximum at that stage. That means you front a large chunk of the land cost yourself. According to RBC Royal Bank (2026).
2

Foundation, framing, systems — each inspected

Draw 2: on the foundation complete and backfilled, after inspection (must be done within 180 days of Draw 1). Draw 3: framing / lock-up — framing, roof, doors and windows in and weather-tight (roughly 35–40% complete). Draw 4: electrical, plumbing, insulation and exterior complete and inspected. Before every draw the lender sends an appraiser/inspector to confirm the work is actually done. According to RBC Royal Bank (2026).
3

Final draw: only at 100% completion

The final advance is released only once the home is 100% complete and the bank’s appraiser confirms it’s affixed to the foundation. During the build you pay interest only on the drawn balance; about a month after completion the loan converts to a regular principal-and-interest mortgage. According to RBC Royal Bank (2026).

⚠️Don’t underestimate the cash-flow gap between draws: the lender pays after each stage passes inspection, and the first draw is capped at ~65% of land value — so early costs (foundation, framing) come out of your own funds or a line of credit before you’re reimbursed. This gap is the classic construction-financing squeeze.

💡 Ontario’s Construction Act (s. 22) requires the owner to hold back 10% of every payment until lien rights expire (generally about 60 days after substantial performance). This protects unpaid trades — if you pay your general contractor the full draw without keeping the 10%, a subcontractor your GC never paid can still register a lien on your home, and you can end up paying twice. Source: Ontario Construction Act / Caravel Law (2026).

Down payment, CMHC and Tarion

Down payment: with CMHC insurance you can build with as little as 5% (5% on the first $500,000, 10% on the balance; home value under $1.5M), and CMHC does insure owner-built / owner-managed construction through progress advances (its full-service option validates up to four draws at no cost). Conventional, uninsured construction lenders typically want 20–25% down. Warranty: new homes built or sold in Ontario need an HCRA-licensed builder and Tarion enrollment; if you self-manage enough to make it a true “owner-built” home, Tarion/HCRA obligations don’t apply and warranties come only from the individual trades. Sources: CMHC (2026); Miller Thomson (2026).

Frequently Asked Questions

Q

Do I need 20%+ down to build a home?

A

Not necessarily. With CMHC insurance you can build with as little as 5% (5% on the first $500,000, 10% on the balance) on homes under $1.5M; conventional, uninsured construction lenders typically want 20–25%. Sources: CMHC / RBC (2026).

Q

Do I start making mortgage payments during construction?

A

During the build you make interest-only payments on the amount drawn so far — no principal. About a month after the home is finished, the loan converts to a normal mortgage and regular principal-and-interest payments begin. Source: RBC (2026).

Q

What’s the 10% holdback and why does it matter to me?

A

Ontario’s Construction Act (s. 22) requires the owner to hold back 10% of each payment to protect unpaid trades. Skip it and an unpaid subcontractor can lien your home even after you’ve paid your general contractor in full — meaning you could pay twice. It’s generally released about 60 days after substantial performance. Source: Ontario Construction Act / Caravel Law (2026).

Q

Do I need a licensed builder and Tarion for a self-build?

A

New homes built or sold in Ontario require an HCRA-licensed builder and Tarion enrollment — unless the project genuinely qualifies as “owner-built” (you have enough control over trades, decisions and materials), in which case Tarion/HCRA obligations don’t apply and warranties come only from the individual trades. Sources: HCRA / Tarion / Miller Thomson (2026).

Q

How fast does the foundation have to go in?

A

On RBC’s product, the foundation must be complete within 180 days of the first draw, and the loan is structured around a one-year build; permit, weather or trade delays past a milestone can trigger re-appraisals or added cost. Other banks (TD, Scotiabank) use different draw counts and percentages — treat this as representative, not universal. Source: RBC (2026).


Discover more from GTA Real Estate Broker | Arthur Zhao

Subscribe to get the latest posts sent to your email.

Continue reading

相关文章Related articles

Mortgage & Finance

The Bank of Canada Doesn’t Set Your Mortgage Rate — Here’s What Actually Does

By its own account, the Bank of Canada does not set mortgage rates — it only influences them, and it influences the two types differently. A fixed rate is driven mostly by the lender’s funding cost (priced in capital markets — economic growth, global rates especially the US, inflation expectations), so it moves even between the Bank’s meetings. A variable rate follows your lender’s own prime, which each lender sets and the Bank’s policy rate influences, moving mainly around eight fixed dates a year. Toronto broker Arthur Zhao uses the Bank’s own 2020 example — a big cut that left new-mortgage rates flat or higher — to take the two chains apart. No live rate numbers; confirm your rate in writing with a licensed mortgage broker or lender.

Aug 13, 2026
贷款与金融

加拿大房贷利率谁说了算:固定与浮动,两条不一样的传导链

很多人以为房贷利率是加拿大央行定的——其实央行明说它并不设定房贷利率,只是影响它们。浮动利率跟的是你贷方自己的 prime,而 prime 由各家贷方设定、受央行政策利率(target for the overnight rate)影响,主要在一年 8 个公告日附近才动;固定利率跟的是贷方的融资成本(由资本市场、全球利率、通胀预期等决定),所以在央行两次会议之间也会变。安省持牌经纪 Arthur Zhao 用央行 2020 年的官方反例把这两条链拆开,教你看对新闻。全文不落任何当日利率数值,具体以持牌按揭经纪/贷方书面确认为准。

Aug 13, 2026
Mortgage & Finance

Mortgage Broker vs. Bank Specialist: Who Actually Works for You

Mortgage broker or bank mortgage specialist — who actually works for you? Arthur Zhao, an Ontario real estate broker, breaks down the structural gap: a broker is FSRA-licensed under the MBLAA and owes you a suitability duty plus written disclosure of how they are paid (O. Reg. 188/08 s.21/24/25), while a bank specialist is a bank employee who sells one institution’s products and is conditionally exempt from that licence (MBLAA s.6(3)), sitting under the federal framework instead. No specific rates or lenders named — confirm terms in writing with a licensed broker or the lender.

Aug 13, 2026
您好!想了解房产买卖、投资、贷款?随时问我。 点这里开聊 →
Arthur Zhao

AZ 房产 AI 顾问

Arthur Zhao · Real Estate Broker